S/No
|
Project Description
|
Contractor
|
Status
|
LGA
|
State
|
Contract Sum
|
1
|
THE REHABILITATION OF NDDC ABIA STATE OFFICE COMPLEX AND THE CONSTRUCTION OF ONE ROOM STORE HOUSE, OKEIKPE
|
AQUA-AIR GLOBAL RESOURCES NIG. LTD.
|
Completed
|
UKWA EAST
|
AB
|
55,468,339.50
|
2
|
FOR THE CONSTRUCTION OF PROTOTYPE UNIVERSITY HOSTEL AT MICHEAL OKPARA UNIVERSITY UMUDIKE
|
COSMOBASE CONSORTIUM LIMITED.
|
Completed
|
IKWUANO
|
AB
|
1,401,726,940.88
|
3
|
FOR THE RENOVATION OF CLASS ROOM BLOCK AT ARIAM/ USAKA COMMUNITY PRIMARY SCHOOL ARIAM USAKA, UBAHU COMMUNITY PRIMARY SCHOOL NNEATO UMUNNECHI AND OKIGWE ROAD PRIMARY SCHOOL
|
EJIRON NIGERIA LIMITED
|
Completed
|
IKWUANO UMUNNEOCHI
|
AB
|
72,500,202.00
|
4
|
FURNISHING OF NDDC HOSTEL IN THE FEDERAL UNIVERSITY OF AGRICULTURE UMUDIKE, IKWUANO LGA, ABIA STATE
|
KENOCHIL SERVICES NIG LTD
|
Completed
|
IKWUANO
|
AB
|
89,812,800.00
|
5
|
COMPLETION OF DINNING HALL AND KITCHEN AT FEDERAL GIRLS COLLEGE, UMUAHIA, ABIA STATE
|
MAROKES PROCUREMENT & LOGISTICS LTD
|
Completed
|
UMUAHIA
|
AB
|
99,975,174.50
|
6
|
FOR THE RENOVATION OF UMUEKECHI HIGH SCHOOL ASA NORTH AUTONOMOUS COMMUNITY
|
ONE DAY CAPITAL RESOURCES & INVST. LTD.
|
Completed
|
UKWAWEST
|
AB
|
23,359,635.50
|
7
|
FOR THE RENOVATION OF CLASS ROOM/HEAD MASTER'S OFFICE AT NATIONAL WEST PRIMARY SCHOOL OBAHU, IKWERRE GIRLS SECONDARY SCHOOL OHAMBELE AND UMUELECHI SECONDARY SCHOOL OBUZOR, ASA UKWAWEST
|
PRE-HORCH OIL & GAS NIG. LIMITED
|
Completed
|
UKWAWEST
|
AB
|
149,004,899.50
|
8
|
SKILL ACQUISITION FOR ABIA STATE AT IGBERE, BENDE LGA
|
SHARLOTTE CONSTRUCTION LIMITED
|
Completed
|
BENDE
|
AB
|
99,890,000.00
|
9
|
CONTRACT FOR ESTABLISHMENT OF AQUACULTURE TRAINING CENTRE, LOT 2 (UMUAHIA) ABIA STATE.
|
SOBAI INTEGRATED SERVICES LTD.
|
Completed
|
UMUAHIA SOUTH
|
AB
|
245,000,000.00
|
10
|
THE CONSTRUCTION OF UMUOKOMIRI INTERNAL ROAD IN UKWAWEST
|
STEEL CREST LIMITED
|
Completed
|
UKWAWEST
|
AB
|
239,750,000.00
|
11
|
HEALTH CENTRE
|
ZOMAX INDUSTRIES LTD.
|
Completed
|
UKWAWEST
|
AB
|
22,260,078.60
|
12
|
INSTRUCTIONTO URGENTLY CLEAR/DESILT BLOCKED SECTIONS OF EZENDIOMA RIVER (LOT 2),UKWAWEST/EAST LGA, ABIA STATE
|
CLARKSON NIG. LTD.
|
Completed
|
UKWAWEST/EAST
|
AB
|
893,631,375.00
|
13
|
INSTRUCTIONTO URGENTLY CLEAR/DESILT BLOCKED SECTIONS OF EZENDIOMA RIVER (LOT 3),UKWAWEST/EAST LGA, ABIA STATE
|
COLLINSGATE NIG. LTD.
|
Completed
|
UKWAWEST/EAST
|
AB
|
892,001,250.00
|
14
|
INSTRUCTIONTO URGENTLY CLEAR/DESILT BLOCKED SECTIONS OF EZENDIOMA RIVER (LOT 1),UKWAWEST/EAST LGA, ABIA STATE
|
GICAN OIL LTD.
|
Completed
|
UKWAWEST/EAST
|
AB
|
898,521,750.00
|
15
|
INSTR.TO URGENTLY CELAR/DESILT BLOCKED SECTIONS OF EMENKPA-NKPAWATERS (LOT 2), UMUAHIA NORTH LGA, ABIA STATE
|
JUST ROYAL NETWORKS LTD.
|
Completed
|
UMUAHIA NORTH
|
AB
|
558,528,632.81
|
16
|
INSTRUCTION OF URGENTLY CLEAR / DESILT BLOCKED SECTIONS OF OBII RIVER, OFEME UMUAHIA. (LOT 2) UMUAHIA NORTH LGA, ABIA STATE
|
STONEFIELD LTD
|
Completed
|
UMUAHIA NORTH
|
AB
|
762,313,125.00
|
17
|
THE INSTALLATION OF 1 NO. 300KVA 33/0.415KVTRANSFORMER AT UMUIWE AUTONOMOUS COMMUNITY UTURU
|
ABANUOGUVENTURES
|
Completed
|
AROCHUKWU
|
AB
|
7,229,545.74
|
18
|
SOLAR POWERED STREET LIGHT AT SELECTED COMMUNITIES (UMUEBULUNGWU AND OBORHIA ASA ), UKWAWEST L.G.A, ABIA STATE
|
ANOGA INTERNATIONAL CONSTRUCTION COMPANY LTD
|
Completed
|
UKWAWEST
|
AB
|
240,000,000.00
|
19
|
CONTRACT FOR THE SOLAR STREET LIGHT AT IKWUORIEATOR EAST/IGUBEACHARA-UKWA EAST LGA, ABIA STATE
|
AVC ENERGY LTD
|
Completed
|
UKWA EAST
|
AB
|
199,350,000.00
|
20
|
INSTALLATION OF 1 NO.TRANSFORMER AT OKPUTU-ONICHA IMIYI-UHU IN ISUIKWATO
|
BENICK & SONS
|
Completed
|
UKWAWEST
|
AB
|
4,500,000.00
|
21
|
THE AWARD OF CONTRACT FOR THE REHABILITATION AND MAINTENANCE OF SOLAR STREET LIGHT IN THE NIGER DELTA REGION, ABIA STATE (LOT 1).
|
CONTACT CONSTRUCTION & BUILDING SERVICES LTD
|
Completed
|
UKWAWEST
|
AB
|
200,000,000.00
|
22
|
INSTALLATION OF TRANSFORMER AT AZUMINI NDOKI, UKWA EAST LGA
|
EDSUNTECHNICAL SERVICES CO
|
Completed
|
UKWA EAST
|
AB
|
9,000,000.00
|
23
|
INSTALLATION OF 1-NO.TRANSFORMER AT LANDLORDS &TENANTS ASSOCIATION, NWAGBOSO STREET, ABA, ABIA STATE
|
FIBBECLIFF SERVICES
|
Completed
|
ABA
|
AB
|
4,500,000.00
|
24
|
AWARD OF CONTRACT FOR INSTALLATION OF SOLAR STREET LIGHT AT OKAIUGA NKEORIE IN UMUAHIA NORTH LGA, ABIA STATE.
|
FRIO NIG. LTD
|
Completed
|
UMUAHIA NORTH
|
AB
|
150,000,000.00
|
25
|
FOR THE PROVISION OF SOLAR POWERED STREET LIGHT AT UMUOREHI- AMAFOR-ISINGWU ROAD UMUAHIA
|
GOLOG-SYNERGIES
|
Completed
|
UMUAHIA SOUTH
|
AB
|
149,500,000.00
|
26
|
CONTRACT FOR THE PROVISION OF SOLAR POWERED STREET LIGHT AT UMUOREHI- AMAFOR-ISINGWU ROAD UMUAHIA
|
GOLOG-SYNERGIES LTD.
|
Completed
|
UMUAHIA SOUTH
|
AB
|
149,500,000.00
|
27
|
THE INSTALLATION OF 1 NO. 300KVA 33/0.415KVTRANSFORMER AT UMUORU VILLAGE
|
HUMAMICH SERVICES NIG. LTD.
|
Completed
|
OBINGWA
|
AB
|
6,841,984.23
|
28
|
THE INSTALLATION OF 1 NO. 500KVA 33/0.415KVTRANSFORMER AT AMUZUKWU IBEKU COMMUNITY
|
HUMAMICH SERVICES NIG. LTD.
|
Completed
|
UMUAHIA NORTH
|
AB
|
4,500,000.00
|
29
|
INSTALLATION OF TRANSFORMER AT ISIUGWU COMMUNITY. OHAFIA
|
INEGBESON INTEGRATED SERVICES
|
Completed
|
OHAFIA
|
AB
|
6,449,392.48
|
30
|
THE CONSTRUCTION OF SOLAR STREET LIGHTS AT UMU-OSU-AHIA MORIE
|
INTERCASPIAN LIMITED
|
Completed
|
UMUAHIA SOUTH
|
AB
|
149,500,000.00
|
31
|
AWARD OF CONTRACT FOR THE INSTALLATION OF 1 NO. 300KVA, 11/0.415KVTRANSFORMER AT AMANKWO UMUOKPARA, UMUAHIA
|
KEVICOMMS NIG. LTD.
|
Completed
|
UMUAHIA
|
AB
|
5,155,758.40
|
32
|
INSTALLATION OF 2 NO. 500KVA/33/0.415KVTRANSFORMER AT OLOKORO WELFARE ASSOCIATION, UMUAHIA SOUTH LGA AND OGWE COMMUNITY
|
K-MMALIC OPTIMUM SERVICES LTD
|
Completed
|
UMUAHIA SOUTH
|
AB
|
12,867,250.00
|
33
|
INSTALLATION OF 3-NOS. 300KVA, 11/0.415KVTRANSFORMERS AT UMUNGEDE, ISIETITE OHA COMMUNITIES OWAZA AND OLD ABA ROAD, UKWAWEST LGA, ABIA STATE
|
LA PRESSY LIMITED
|
Completed
|
UKWAWEST
|
AB
|
13,500,000.00
|
34
|
INSTALLATION OF 300KVA/11KVATRANSFORMER AT IKEMGBOKO, OZATTA, IKEALA AHIABA AND UMUDUKWU EHERE, OBINGWA LGA, ABIA STATE
|
LARISA GLOBAL PROSPECTS LTD.
|
Completed
|
None
|
AB
|
18,000,000.00
|
35
|
INSTALLATION OF 2-NOS. 300KVATRANSFORMER AT AROCHUKWU AND OBIOHIA NDOKI, UKWA EAST LGA, ABIA STATE
|
LATESMOORE KONCEPTS COMPANY
|
Completed
|
UKWA EAST
|
AB
|
9,000,000.00
|
36
|
THE INSTALLATION OF 1 NO. 500 KVA, 33/0.415KVATRANSFORMER AT ABIA STATE UNIVERSITY, UTURU
|
LEMANTIC & CO. CONSTRUCTION NIG. LIMITED
|
Completed
|
UTURU
|
AB
|
7,522,529.74
|
37
|
CONTRACT FOR THE INSTALLATION OF 1 NO. 300KVA/0.415KVTRANSFORMER AT NDIEGORO COMMUNITY ASA, ABA SOUTH, ABIA STATE
|
LEWISMMA INTEGRATED SERVICES LTD
|
Completed
|
ABA SOUTH
|
AB
|
6,240,641.97
|
38
|
INSTALLATION OF 1 NO. 300KVA 33/0.415KVTRANSFORMER AT OWAZA, UKWAWEST LGA, ABIA STATE
|
LUCHIMS CONSTRUCTION COY. LTD
|
Completed
|
UKWAWEST
|
AB
|
7,625,251.25
|
39
|
FOR THE INSTALLATION OF 1NO. 300KVA/11, TRANSFORMER AT ODE-UKWU AUTONOMOUS COMMUNITY, ISIALA NGWA NORTH LGA
|
MABIS NIGERIA LTD.
|
Completed
|
ISIALA NGWA NORTH
|
AB
|
4,500,000.00
|
40
|
THE SOLAR POWERED STREET LIGHT AT MGBARA-OGBOM ROADTO UMUOBRIOLA ROAD, UMUAHIA SOUTH L.G.A.[RELOCATEDTO UMUORGU- ISI-ALA NTEKE ASA] UKWAWEST L.G.A.
|
MIBURGH ENGINEERING LTD.
|
Completed
|
UKWAWEST
|
AB
|
199,487,785.50
|
41
|
INSTALLATION OF 1-NO. 300KVA, TRANSFORMER AT AKWETE, UKWA EAST LGA, ABIA STATE
|
MUTUAL BOND SERVICES
|
Completed
|
UKWA EAST
|
AB
|
4,500,000.00
|
42
|
AWARD OF CONTRACT FOR THE CONSTRUCTION OF SOLAR POWERED STREET LIGHT FROM NKWUNABARTOWER ROAD IN AMONNAGWU VILLATO EZE ARO PALACE ROAD, ORRO VILLA, AROCHUKWU LGA
|
NGOSAMTECHNICALVENTURE
|
Completed
|
AROCHUKWU
|
AB
|
239,560,750.00
|
43
|
FOR THE INSTALLATION OF 500 KVA 33/0.415 KV AND 300KVA, 11/0.415 KVTRANSFORMERS AT UMUELECHITOWN, ISI-OBUZOR COMMUNITY AND IHIE NDUME, UMUAHIA, DOZIEWAY NEIGHBOURHOOD
|
ONE DAY CAPITAL RESOURCES
|
Completed
|
UKWAWEST/ UMUAHIA NORTH
|
AB
|
12,720,755.00
|
44
|
THE INSTALLATION OF TRANSFORMERS AND POWER IMPROVEMENT AT AMIGO, AMABO, OKOKO ITEM BENDE
|
OX-MAT RESOURCES LIMITED
|
Completed
|
BENDE
|
AB
|
20,000,000.00
|
45
|
POWER IMPROVEMENT PROJECT AT OHANKU, ISIALA NTEKE, OHURU, OBORHIA IN UKWAWEST/ EAST LGA, ABIA STATE
|
OX-MAT RESOURCES LTD
|
Completed
|
UKWAWEST/UKWA EAST
|
AB
|
233,629,845.95
|
46
|
AWARD OF CONTRACT FOR THE ELECTRIFICATION OF UMUIHIE, UMUAHIA SOUTH LGA
|
PREHORCH OIL & GAS NIG. LTD.
|
Completed
|
None
|
AB
|
91,474,239.00
|
47
|
PROVISION OF SOLAR STREET LIGHT IN UMUEHIE-ODO AT UMUAHIA SOUTH LGA,
|
RIEN CHEMIE NIG. LTD
|
Completed
|
UMUAHIA SOUTH
|
AB
|
149,941,050.00
|
48
|
CONSTRUCTION OF SOLAR POWERED STREET LIGHT AT AZUMINI, OHAMBELE, OBEAKU AND AKWETTE
|
SOLBEC LIMITED
|
Completed
|
UKWA EAST
|
AB
|
245,000,000.00
|
49
|
CONSTRUCTION OF SOLAR POWERED STREET LIGHTS AT AZUMINI, OHAMBELE, OBEAKU AND AKWETE COMMUNITIES, UKWA EAST LGA, ABIA STATE
|
SOLBEC LIMITED
|
Completed
|
UKWA EAST
|
AB
|
245,000,000.00
|
50
|
PROVISION OF SOLAR STREET LIGHT IN UMUIKUKOR AT UKWAWEST LGA,
|
SPACE HOLDINGS LTD
|
Completed
|
UKWAWEST
|
AB
|
149,941,050.00
|